Cranes and FAA Form 7460-1: when temporary equipment needs notice

Cranes count. A tower or mobile crane that exceeds the Part 77 notice criteria needs its own Form 7460-1, filed at least 45 days before it goes up.

Updated 2026-10-03 · Not legal advice — always confirm with the agency.

Cranes are structures for FAA purposes

Under 14 CFR Part 77, temporary construction equipment — tower cranes, mobile cranes, drill rigs, pile drivers — is treated like any other structure. If the crane's maximum height exceeds the notice criteria in 14 CFR 77.9, it needs its own Form 7460-1, even when the building it's constructing doesn't.

How to measure crane height

Timing

File at least 45 days before the crane goes up. Crane filings commonly get shorter-term determinations covering the construction period. If the crane height or position changes, file a revised notice.

Quick reference: when a crane needs notice

Distance from runway (airport with a runway > 3,200 ft)Notice if taller than (above runway elevation)
1,000 ft10 ft
5,000 ft50 ft
10,000 ft100 ft
20,000 ft200 ft
Anywhere200 ft above ground

If your site sits lower than the runway, you get extra room; if it sits higher, you get less. The free check above does this calculation for your exact spot.

Common questions

Can the crane and the building share one filing?

No — file the permanent structure and each crane separately.

What if the crane is only up for a week?

Duration doesn't change the requirement. If it exceeds the criteria, it needs notice.

Who files — the general contractor or the crane company?

Whoever is proposing the construction (the “sponsor”) is responsible; on most projects the general contractor or crane provider files.